Western Placerville Interchange Phase 1A - Westbound US 50 On Ramp |
Description: In the City of Placerville, at the Forni Road/Placerville Drive/US 50 Interchange. Construct the Westbound US 50 Onramp component of the Ray Lawyer Drive Interchange.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
El Dorado |
City | Placerville |
Zip Code | 95667 |
Senate District |
01 |
Assembly District | 04 |
Congressional District | 04 |
Caltrans District |
03 |
County/State Route | El Dorado 50 |
Postmile Begin/End | 16 16.6 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 88 | 88 |
Lane Miles Added (HOV) | 0 | |
Lane Miles Added (Mixed) | 0.5 | |
Peak Period Time Savings (minutes) | 4075 | 4,075 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
City of Placerville | Rebecca Neves | (530)642-5250 | rneves@cityofplacerville.org | |
Design (PS&E) Phase |
City of Placerville | Rebecca Neves | (530)642-5250 | rneves@cityofplacerville.org | |
Right of Way Phase |
City of Placerville | Rebecca Neves | (530)642-5250 | rneves@cityofplacerville.org | |
Construction Phase |
City of Placerville | Rebecca Neves | (530)642-5250 | rneves@cityofplacerville.org | |
Corridor System Management Plan |
City of Placerville | Nathan Stong | (530)642-5250 | nstong@cityofplacerville.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
CMIA |
$6,000 | $0 | $6,000 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Local** |
$3,145 | $0 | $3,145 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $9,145 | $0 | $9,145 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$1,075 | $0 | $1,075 | $1,073 | |||
Design(PS&E) |
$2,070 | $0 | $2,070 | $2,065 | |||
Right of Way |
$0 | $0 | $0 | $0 | |||
Construction |
$6,000 | $0 | $6,000 | $5,993 | |||
Total* | $9,145 | $0 | $9,145 | $9,131 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
|
|
10/01/2002 01/15/2009 |
100 | 10/01/2002 01/15/2009 |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
02/13/2007 05/18/2012 |
|
05/02/2009 07/02/2012 |
100 | 05/02/2009 07/02/2012 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
01/01/2012 04/12/2012 |
|
10/01/2009 04/12/2012 |
100 | 10/01/2009 04/12/2012 |
0 0 |
|
Begin Construction Phase
End Construction Phase |
08/17/2012 10/15/2013 |
|
11/05/2012 11/30/2014 |
0 | 11/05/2012 11/30/2014 |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
11/01/2013 01/15/2014 |
|
11/30/2014 02/01/2017 |
50 | 11/30/2014 01/07/2019 |
0 -23 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 0 | 0 | |||||
Implementation Date | 0 | 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 88 | 88 |
Lane Miles Added (HOV) | 0 | |
Lane Miles Added (Mixed) | 0.5 | |
Peak Period Time Savings (minutes) | 4075 | 4,075 |
Bond Funding Cost | |
---|---|
Adopted: |
$6,000,000 |
Current Approved: |
$6,000,000 |
Actual Expenditures: |
$5,993,000 |
Status as of December 31, 2023.