Western Placerville Interchange Phase 1A - Westbound US 50 On Ramp

Description: In the City of Placerville, at the Forni Road/Placerville Drive/US 50 Interchange. Construct the Westbound US 50 Onramp component of the Ray Lawyer Drive Interchange.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
El Dorado
City Placerville
Zip Code 95667
 
Senate District
01
Assembly District 04
Congressional District 04
 
Caltrans District
03
 
 
County/State Route El Dorado 50
Postmile Begin/End 16 16.6
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  88    88  
Lane Miles Added (HOV)      0  
Lane Miles Added (Mixed)      0.5  
Peak Period Time Savings (minutes)  4075    4,075  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Placerville Rebecca Neves (530)642-5250   rneves@cityofplacerville.org
Design (PS&E) Phase
City of Placerville Rebecca Neves (530)642-5250   rneves@cityofplacerville.org
Right of Way Phase
City of Placerville Rebecca Neves (530)642-5250   rneves@cityofplacerville.org
Construction Phase
City of Placerville Rebecca Neves (530)642-5250   rneves@cityofplacerville.org
 
Corridor System Management Plan
City of Placerville Nathan Stong (530)642-5250   nstong@cityofplacerville.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$6,000 $0 $6,000
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$3,145 $0 $3,145
Non Budgeted ETC
$0 $0 $0
 
Total**** $9,145 $0 $9,145

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$1,075 $0 $1,075 $1,073
Design(PS&E)
$2,070 $0 $2,070 $2,065
Right of Way
$0 $0 $0 $0
Construction
$6,000 $0 $6,000 $5,993
 
Total* $9,145 $0 $9,145 $9,131

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
10/01/2002 

01/15/2009 
100  10/01/2002 

01/15/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/13/2007 

05/18/2012 
 

 
05/02/2009 

07/02/2012 
100  05/02/2009 

07/02/2012 


Begin Right of Way Phase

End Right of Way Phase
01/01/2012 

04/12/2012 
 

 
10/01/2009 

04/12/2012 
100  10/01/2009 

04/12/2012 


Begin Construction Phase

End Construction Phase
08/17/2012 

10/15/2013 
 

 
11/05/2012 

11/30/2014 
11/05/2012 

11/30/2014 


Begin Closeout Phase

End Closeout Phase
11/01/2013 

01/15/2014 
 

 
11/30/2014 

02/01/2017 
50  11/30/2014 

01/07/2019 


-23 
Corridor System Management Plan
Adoption Date        
Implementation Date        
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 88 88
Lane Miles Added (HOV) 0
Lane Miles Added (Mixed) 0.5
Peak Period Time Savings (minutes) 4075 4,075

Bond Funding Cost
Adopted:
$6,000,000
Current Approved:
$6,000,000
Actual Expenditures:
$5,993,000

 

Status as of December 31, 2023.